The expected traffic impacts in District 3 for August 27 through August 31 are listed below. All work is subject to change. For more information checkout the new GoKY.ky.gov. Follow District 3 on Twitter @kytcdistrict3 and Facebook @kytcdistrict3.

Interstate 65

Preparations for a major resurfacing project has started on I-65 in both directions from mile marker 35 to mile marker 44. Construction barrels have been placed on the shoulders as crews are working on drainage pieces. The actual milling and resurfacing is expected to start on Tuesday, September 4 and is expected to last a couple of months. Motorists need to slow down while traveling in this area. There will preparation work going in the area until the resurfacing project stats. There will be some lane closures next week from 7 p.m. to 7 a.m. for prep work.

Logan County

US 431 Lewisburg Road from KY 3519 extending to the Muhlenberg County line - Contract crews will begin resurfacing this 10-mile section of road. Motorists should anticipate a one-lane roadway controlled by flaggers and use should caution through this work zone.

US 68/KY 80 between mile points 20-25 - A resurfacing project near Auburn in Logan County will continue this week. Motorists should expect lane closures and need to use caution while traveling in the area during resurfacing. The speed limit is reduced to 55 mph. Signs and message boards have been placed to warn motorists.

Simpson County

US 31-W Nashville Road- Paving operations are complete on this project. Crews will continue to be present putting the finishing touches on the project but most remaining work will take place of the roadway. Motorist should still use caution while traveling in the area.

KY 100 west from KY 1008 to Logan County line- Crews will be present to continue work on a resurfacing and curve improvement project in the area. Work will begin on base failure repairs as well as continue on pipe replacements and excavation for the project. Flaggers will be used at various stages of the project and motorist should use caution when traveling the area.

KY 585 Gold City Road-Crews will be present and working on pipe replacements in preparation for a resurfacing job from the Allen Simpson County line to KY 622. Flaggers will be present and traffic down to one lane during working hours.

Todd County

US 41 Dixie Bee Line Highway from KY 346 extending to the Christian County line - Contract crews will finish resurfacing operations along this 12-mile section of roadway. Motorists should anticipate a one-lane roadway controlled by flaggers and use caution through this work zone.

KY 1753 Elkton Trenton Road from KY 104 extending to KY 181- Contract crews will finish resurfacing operations along this section of roadway. Motorists should anticipate a one-lane roadway controlled by flaggers and use caution through this work zone.

Warren County

KY 2629 Old Scottsville Road – Base Failures will be completed today and they will have to settle out for a week so there should be little to no work going on out there next week but paving is scheduled to begin the following week.

KY 884 Three Springs Road – From KY 242 to KY 240 paving has begun and will finish up early next week.

KY 101 – A preventive maintenance project on KY 101 in Warren County is expected to begin tomorrow. A cape seal project will be completed to extend the life of the current pavement on KY 101 from the intersection with US 31-W (mile point 11.6) to the Edmonson County line (mile point 12.8). Motorists need to use slower speeds until the project is completed.

I-65 to US 31-W Connector– The contractor will continue working in the area to move towards the tie into US 31W. This tie in is scheduled to be done by the end of the year. Minor traffic impacts are expected.

US 68 Veteran’s Memorial – There will be some lane closures in various spots for a triathlon race on the morning of Sunday, August 26.